Upgrade or Downgrade Your Electricity Supply
Single-phase vs. Three-phase Supply
Generally, you should change to a 3-phase supply if you have three (3) or more air-conditioners in your home. Upgrading to a 3-phase supply will increase stability and reliability of electricity supply to your premises.
A single-phase meter measures usage from a 230 volt supply through two (2) wires, while a 3-phase meter measures usage from a 415 volt supply through four (4) wires.
You are advised to change from a single-phase supply to a 3-phase supply when your household electricity load exceeds 10kW (or 50A).
How to apply for Upgrade or Downgrade Supply Application?
Just login to www.mytnb.com.my to submit your request online. You would will be required select the preferred contractor and to clear outstanding payment (if any) online. This service is applicable to:
- Individual (Residential Category) Customers
- TNB Registered Electrical Contractors
Note: Online application is only applicable for maximum demand of 60kW (or 100A) only. For Large Power Consumers (LPC), application must be made through Kedai Tenaga.
Benefits of Upgrade/Downgrade Supply Application Online
- Faster application
- Online Electrical Contractor selection and appointment
- Real-time supply application status updates
- Check amount of Connection Charges and Supply Deposit
- Immediate online payment for connection charges, security deposit and stamp duty
Note: Due to legal restrictions, contractual documents will need to be signed off manually and attach it back into the system.
What is the application process for Upgrade/Downgrade Supply Application through online?
Online Application
Appoint Contractor
|
|
Fill Up Form
|
|
Pay Essential Charges
|
|
Get Electricity Supply
|
Note: Currently under this category, customers are required to pay upfront all these essential charges which include the Connection Charges, Stamp Duty and Security Deposit to apply for electricity. To get the best deal among the listed contractors, customers are advised to liaise and request for quotations prior to appointing one.
Required Documents
REQUIRED DOCUMENTS BY APPLICANT |
UNDER PERSONAL NAME |
COMPANY / SOLE PROPRIETORSHIP / ENTERPRISE / PARTNERSHIP / SOCIETY |
GOVERNMENT BODY / AGENCIES |
Completed & Signed Application Form (Malay or English)
|
✓
|
✓
|
✓
|
Copy of Applicant’s Identification Document
|
✓ - |
IC Copy of Authorized Person / Representative
|
IC Copy of Authorized Person / Representative (Optional)
|
Letter of Authorization with Company Letterhead
|
Letter of Authorization with Government / Agency Letterhead
|
||
Copy of Registration Certificate
|
-
|
✓
|
-
|
REQUIRED DOCUMENTS BY THE APPOINTED ELECTRICAL CONTRACTOR |
|||
✓ |
|||
Metering Schematic (for Maximum Demand >100A) |
✓ |