Upgrade or Downgrade Your Electricity Supply

Single-phase vs. Three-phase Supply

Generally, you should change to a 3-phase supply if you have three (3) or more air-conditioners in your home. Upgrading to a 3-phase supply will increase stability and reliability of electricity supply to your premises.
A single-phase meter measures usage from a 230 volt supply through two (2) wires, while a 3-phase meter measures usage from a 415 volt supply through four (4) wires.
You are advised to change from a single-phase supply to a 3-phase supply when your household electricity load exceeds 10kW (or 50A).

How to apply for Upgrade or Downgrade Supply Application?

Just login to www.mytnb.com.my to submit your request online. You would will be required select the preferred contractor and to clear outstanding payment (if any) online. This service is applicable to:

  • Individual (Residential Category) Customers
  • TNB Registered Electrical Contractors

Note: Online application is only applicable for maximum demand of 60kW (or 100A) only. For Large Power Consumers (LPC), application must be made through Kedai Tenaga.

Benefits of Upgrade/Downgrade Supply Application Online

  • Faster application
  • Online Electrical Contractor selection and appointment
  • Real-time supply application status updates
  • Check amount of Connection Charges and Supply Deposit
  • Immediate online payment for connection charges, security deposit and stamp duty

Note: Due to legal restrictions, contractual documents will need to be signed off manually and attach it back into the system.

What is the application process for Upgrade/Downgrade Supply Application through online?

COA flow1

Online Application

Appoint Contractor

COA flow2

Fill Up Form

  • Customer fills the electricity online application form, signs the digital electricity supply contract (electricity application form) with TNB
COA flow3

Pay Essential Charges

  • TNB comes up with the connection charges relevant with the electricity connection
  • Customer pays the connection charges and RM10 stamp duty online or at Kedai Tenaga
COA flow4

Get Electricity Supply

  • Customer pays the electricity deposit
  • TNB installs meter and connects supply

 

Note: Currently under this category, customers are required to pay upfront all these essential charges which include the Connection Charges, Stamp Duty and Security Deposit to apply for electricity. To get the best deal among the listed contractors, customers are advised to liaise and request for quotations prior to appointing one.

Required Documents

REQUIRED DOCUMENTS BY APPLICANT

UNDER PERSONAL NAME

COMPANY / SOLE PROPRIETORSHIP / ENTERPRISE / PARTNERSHIP / SOCIETY

GOVERNMENT BODY / AGENCIES

Completed & Signed Application Form

 

 

 

 

Copy of Applicant’s Identification Document

 


-

IC Copy of Authorized Person / Representative

 

IC Copy of Authorized Person / Representative (Optional)

 

Letter of Authorization with Company Letterhead

 

Letter of Authorization with Government / Agency Letterhead

 

Copy of Registration Certificate

 

-

 

 

-

 

REQUIRED DOCUMENTS BY THE APPOINTED ELECTRICAL CONTRACTOR

Form G - Supervision and completion certificate

Form H - Test Certificate

Metering Schematic (for Maximum Demand >100A)